2 - General Conditions & Requirements – Excavation E-Permits

Revised on 10-04-2024

GENERAL CONDITIONS OR REQUIREMENTS


Excavation “E” Permits (formerly known as Special Deposit Permits) are for the installations, inspection, repair, abandonment or removal of any tank, pipe, conduit duct, tunnel, or footing, or for any other purpose, or for any excavation on private property adjacent to a public street where lateral support to such street or improvements or property within such street is imperiled by the excavation.

PERMITTEE OBLIGATIONS AND REQUIREMENTS (LAMC 62.02)


graphic of a checklist Permittees are responsible for fulfilling conditions per LAMC 62.02, LAMC 62.03, LAMC 62.04 and paying fees in person per LAMC 62.05(a)(1)

Applicants are encouraged to apply for an Excavation “E” permit on-line. Payment must be made in person at the Public Counter of the applicable District office.

Depending on the E-Permit being applied for the submittal requirements are specified within each document under E-Permit Technical Procedures.  For all E-Permits, a dimensioned and drawn-to-scale engineering plan is required for projects when requested by the City permit engineer.  All work shall be in accordance with the BOE’s Standard Plans which are available on the Internet at http://eng2.lacity.org/techdocs/stdplans/index.htm.

SAFETY


Graphic of a safety cone Lights and Barricades

Safety requirement for Excavation E Permits shall follow the Safety Guidelines for Development Services permits.

 

PEAK HOUR RESTRICTIONS


Peak hour restrictions and exemptions for Excavation U Permits shall follow the Peak Hour Restrictions/Exemptions Guidelines for Development Services permits.